Timeline
- Comment Form Deadline: November 15, 2019
- Master Plan Board Approval: February 2020
- Design Development: January - March 2020
- Construction Documents: April - August 2020
- Bidding Process: August - October 2020
- Construction (weather dependent): December 2020 - July 2021
- Plant Establishment: June 2021
- Open to the Public: August 2021