Administration Building Updates

In the early morning hours of February 20, 2015, the Cosumnes Community Services District Administration Building suffered significant fire damage. Located at 8820 Elk Grove Blvd., the 94-year-old building was a familiar landmark in the community. 

This page will be updated with details pertaining to the design development, project bidding, and construction phases of the CSD Administration Building Reconstruction Project.

CSD Administration Building Reconstruction Project


The rebuilding process cannot begin until the insurance claim is settled and the space is designed to fit the District.  Although unfortunate, the fire has provided the District the opportunity to better use the existing square footage, modernize the space, and provide amenities that are desirable to staff.  MFDB Architects, Inc. has been retained by the District to lead the design of the building.

Phase Schedule

Phase Progress
Concept Plan

Completed - Presented to the Board on 1/20/16
View Staff Report

Schematic Design Est. Completion: Spring 2016
Design Development

Est. Completion: Summer 2016

Construction Document Est. Completion: Winter 2016
Bidding and Bid Award Est. Completion: Spring 2017
Contract Finalization Est. Completion: Spring 2017
Project Construction Est. Completion: Summer 2018

Concept Plan Drawing - Back of CSD Administration Building (looking North)

CSD New Admin Bldg CP drawing
If you have further questions or media requests, please contact Bob Roessler, Parks and Recreation Administrator, at 916-405-5300.